ONGOING PROJECTS

NAME OF THE CONTRACT COUNTRY EMPLOYER DATE OF CONTRACT STATUS LINE LENGTH (km) NUMBER OF TOWERS
EPC FOR HV POWER TRANSMISSION SYSTEM ZUBAIR PROJECT - IRAQ (Contract No. 211/2011/NR/ZU) IRAQ ENI OIL COMPANY 25/03/2014 95% Complete and at Commissioning phase(Estimated Completion in March 2019) 160,0 500+
380 kV (158 km) 2X3B 1272 MCM Conductor Bandırma DGKÇS TURKEY TURKISH ELECTRICITY AUTHORITY 06/07/2017 40% Complete and (Estimated Completion in June 2019) 158,0 419
380 kV (~159 km) DC ve (~10,3 km) SC 3B 1272 MCM Conductor Verbena DGKÇS-Alibeyköy Transmission Line (H334T) TURKEY TURKISH ELECTRICITY AUTHORITY 06/06/2017 78% Complete and (Estimated Completion in May 2019) 169,0 132
380 kV (126 km) 3B 1272 MCM Conductor İspir-Köse ile 380 kV (6,1 km) 3B 1272 MCM + 154 kV (0,4 km) 2X1272 MCM Conductor Transmission Line (H362) TURKEY TURKISH ELECTRICITY AUTHORITY 28/04/2017 56% Complete and (Estimated Completion in June 2019) 133,0 334